GIS Project Management Flashcards
7 cards from real GISP practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 GIS Project Management flashcards as text
Which project management document formally authorizes a GIS project and grants the project manager authority to apply organizational resources?
Answer: Project charter
The project charter is the document that formally authorizes the project and gives the project manager the authority to use organizational resources.
In GIS project planning, a Work Breakdown Structure (WBS) is used primarily to:
Answer: Decompose project deliverables into manageable components
A WBS decomposes the total scope of work into smaller, manageable components called work packages to facilitate planning and control.
Which scheduling technique uses the longest path through a project network to determine the minimum project duration?
Answer: Critical Path Method (CPM)
The Critical Path Method identifies the longest sequence of dependent tasks, which determines the earliest possible project completion date.
A GIS project manager is using Earned Value Management (EVM). If the Schedule Performance Index (SPI) is 0.80, what does this indicate?
Answer: The project is progressing at 80% of the planned rate
An SPI of 0.80 means the project is earning only $0.80 of planned value for every $1.00 of scheduled work, indicating it is behind schedule.
When managing a GIS project, which risk response strategy involves transferring the negative impact of a risk to a third party?
Answer: Risk transference
Risk transference shifts the ownership of a risk and its response to a third party, such as through insurance or outsourcing.
In the context of GIS project management, which document defines what is and is not included in a project?
Answer: Project scope statement
The project scope statement clearly documents the project boundaries, deliverables, and exclusions to prevent scope creep.
Which agile project management framework uses fixed-length iterations called sprints, typically lasting 2–4 weeks, and is increasingly applied to GIS software development?
Answer: Scrum
Scrum is an agile framework that organizes work into time-boxed sprints, enabling iterative delivery and continuous improvement in software and GIS development projects.