A gemology lab project is running over budget. The project manager performs Earned Value Analysis and finds CPI = 0.85. What does this indicate?
-
A
The project is ahead of schedule
-
B
For every dollar spent, only $0.85 of value is being delivered
-
C
The project is under budget
-
D
The project schedule is at risk