Project Planning & Execution Flashcards
7 cards from real GCP practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Project Planning & Execution flashcards as text
A project manager is using a responsibility assignment matrix (RAM). In a RACI chart, what does the 'C' stand for?
Answer: Consulted
In RACI, 'C' stands for Consulted, meaning those whose input is sought and with whom there is two-way communication.
During execution, the project team discovers a previously unidentified risk. Where should this risk be documented?
Answer: Risk register
All identified risks, including those discovered during execution, are documented in the risk register for tracking and response planning.
A project's Planned Value (PV) is $120,000 and its Earned Value (EV) is $100,000. What is the Schedule Variance (SV)?
Answer: -$20,000
Schedule Variance = EV − PV = $100,000 − $120,000 = −$20,000, indicating the project is behind schedule.
Which type of dependency occurs when one activity cannot start until another has finished, regardless of any other constraints?
Answer: Mandatory dependency
Mandatory dependencies are contractually or physically required relationships between activities and cannot be changed by the project team.
A project manager wants to identify which risks have the greatest potential impact on project objectives. Which tool is MOST appropriate?
Answer: Tornado diagram
A tornado diagram ranks risks by the range of their potential impact on the project objective, making it easy to identify the highest-priority risks.
Which document formally authorizes a project and gives the project manager authority to apply organizational resources?
Answer: Project charter
The project charter is the document that formally authorizes the project and grants the PM authority to use organizational resources.
A project manager is planning communication for a project with 8 stakeholders. How many potential communication channels exist?
Answer: 28
Communication channels = n(n−1)/2 = 8×7/2 = 28, where n is the number of stakeholders.