Under the Georgia Administrative Procedure Act, what is the minimum notice period an agency must provide before adopting a non-emergency rule?
-
A
10 days after posting on the agency website
-
B
At least 30 days after filing notice with the Secretary of State and publishing in the Georgia Administrative Register
-
C
60 days after mailing notice to all regulated parties
-
D
No advance notice is required if the agency holds a public hearing