Earned Value Management (EVM) VIP Certification Practice Exam
EVM — This exam mirrors the AACE International Earned Value Professional (EVP) certification exam, a credential for practitioners with demonstrated EVM experience; the real exam consists of approximately 100 multiple-choice questions administered over 3 hours with a passing score near 70%, covering EVM principles, ANSI/EIA-748 compliance, planning, performance measurement, forecasting, and reporting.
57
Questions
180m
Time Limit
70.00%
To Pass
Question 1 of 57👑 VIP
A project has a Budget at Completion (BAC) of $500,000 and is currently 40% complete by schedule. The project team has actually completed 35% of the work, and the Actual Cost incurred to date is $190,000. What is the Cost Variance (CV) for this project?
Questions 2–57 and full explanations are VIP-exclusive.