A full-stack developer is asked to estimate a project that will take 3 months. Which estimation technique is most appropriate for reducing overconfidence bias?
-
A
Single-point estimation with a precise date
-
B
Planning Poker with team consensus
-
C
Three-point estimation using optimistic, realistic, and pessimistic scenarios
-
D
Doubling whatever feels right instinctively