Explanation:
Similar cost estimating is a top-down method that is typically less accurate.
Explanation:
All "Manage" processes are part of the "Executing Process Group."
Explanation:
It is crucial to properly carry out a risk identification activity in such circumstances. For initiatives with a high-risk impact, it's crucial to identify all potential risks.
Explanation:
It ought to have been completed at the planning stage.
Explanation:
A risk response technique for mitigating negative risks is called a prototype. A prototype will assist in lowering the risks involved in product development in order to guarantee acceptance of the final product currently in development.
Explanation:
All risks, whether favorable or negative, are listed in the risk registry. Because probability is also significant.
Explanation:
To eliminate biases, the Delphi technique maintains participant anonymity.