A manufacturing company has established an objective to reduce its water consumption by 10%.
They have planned to install new water-efficient fixtures and train employees on water conservation techniques.

The company is now conducting the required training sessions for all staff.

According to the Plan-Do-Check-Act (PDCA) cycle, which phase is the company currently executing?

Select your answer