FRA Track & Roadway Safety 2 — Questions and Answers
Question 1: Under FRA regulations, what is the maximum allowable track gage for Class 1 track?
- 4 feet 8 inches
- 4 feet 9 inches (Correct answer)
- 4 feet 10 inches
- 4 feet 11 inches
Correct answer: 4 feet 9 inches
FRA regulations allow a maximum track gage of 4 feet 9 inches for Class 1 track (56A inches plus 3/4 inch tolerance).
Question 2: Which FRA track class permits the highest freight train speeds?
- Class 3
- Class 4
- Class 5 (Correct answer)
- Class 6
Correct answer: Class 5
Class 5 track permits freight train speeds up to 80 mph, while Class 6 and above apply to passenger-only high-speed operations.
Question 3: A track geometry defect that causes one rail to be higher than the other in a curve is called:
- Cross-level deviation (Correct answer)
- Alignment defect
- Superelevation excess
- Rail cant failure
Correct answer: Cross-level deviation
Cross-level deviation refers to a difference in the heights of the two rails that exceeds allowable tolerances.
Question 4: According to 49 CFR Part 213, how often must Class 3 and 4 track be inspected by a qualified inspector?
- Once per week
- Twice per week (Correct answer)
- Once per month
- Once per day
Correct answer: Twice per week
Class 3 and 4 tracks must be inspected at least twice per week by a qualified track inspector.
Question 5: What is the minimum depth of ballast required under the crosstie for Class 4 track?
- 6 inches
- 8 inches
- 10 inches
- 12 inches (Correct answer)
Correct answer: 12 inches
FRA regulations require a minimum ballast depth of 12 inches under the base of the tie for Class 4 track.
Question 6: A broken rail discovered during a track inspection requires the inspector to:
- Flag the location and report it within 24 hours
- Immediately notify the train dispatcher and restrict or halt traffic (Correct answer)
- Allow one train to pass at restricted speed before shutting down
- Place a blue flag at each end of the break
Correct answer: Immediately notify the train dispatcher and restrict or halt traffic
A broken rail is an immediate safety hazard; the inspector must notify the dispatcher and restrict or stop train movements over the defect.
Question 7: What FRA regulation part governs track safety standards for railroads in the United States?
- 49 CFR Part 209
- 49 CFR Part 211
- 49 CFR Part 213 (Correct answer)
- 49 CFR Part 215
Correct answer: 49 CFR Part 213
49 CFR Part 213 contains the FRA's Track Safety Standards governing geometry, structure, and inspection requirements.
Under FRA regulations, what is the maximum allowable track gage for Class 1 track?