In Earned Value Management (EVM) for a fire sprinkler project, if EV = $80,000 and PV = $100,000, what does this indicate?
-
A
The project is ahead of schedule
-
B
The project is behind schedule
-
C
The project is under budget
-
D
The project has positive cost variance