Florida General Contractor Construction Project Management 4
A guaranteed maximum price (GMP) contract protects the owner by:
Select your answer
A
Capping the total cost the owner will pay, with savings often shared
B
Fixing the contractor's profit at 50 percent
C
Eliminating the need for change orders
D
Removing all contractor liability