โ† All Florida General Contractor Flashcard Decks

Florida General Contractor MCQ Flashcards

7 cards from real Florida General Contractor practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Florida General Contractor MCQ flashcards as text
  1. When bidding a project, what does 'overhead' typically refer to in a contractor's cost estimate?

    Answer: Indirect costs of running the business not tied to one job

    Overhead covers indirect business costs like office rent, insurance, and administration allocated across jobs.

  2. In a lump-sum (fixed-price) contract, who primarily bears the risk of cost overruns?

    Answer: The contractor

    Under a lump-sum contract the contractor absorbs cost overruns because the price is fixed.

  3. What does a 'retainage' provision in a construction contract allow the owner to do?

    Answer: Withhold a percentage of each payment until completion

    Retainage lets the owner hold back a percentage of progress payments as security until the work is complete.

  4. A performance bond primarily protects the owner against what?

    Answer: The contractor failing to complete the contract

    A performance bond guarantees the project will be completed per the contract if the contractor defaults.

  5. What is the purpose of a payment bond on a construction project?

    Answer: To ensure subcontractors and suppliers get paid

    A payment bond guarantees that subcontractors, laborers, and material suppliers are paid.

  6. In critical path method (CPM) scheduling, the critical path represents which of the following?

    Answer: The longest sequence of dependent tasks determining project duration

    The critical path is the longest chain of dependent activities that sets the minimum project duration.

  7. A change order in construction is best described as what?

    Answer: A written modification to the original contract scope, price, or time

    A change order formally documents an agreed modification to the contract's scope, cost, or schedule.