Florida General Contractor Estimating and Bidding Flashcards

6 cards from real Florida General Contractor practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 Florida General Contractor Estimating and Bidding flashcards as text
  1. What does the term 'bid bond' guarantee in a Florida public construction bid?

    Answer: That the contractor will enter into the contract and provide required bonds if awarded the bid

    A bid bond guarantees that if the bidder wins, they will execute the contract and provide required performance and payment bonds.

  2. In construction estimating, what does the term 'contingency' refer to?

    Answer: A reserve added to the estimate to cover unforeseen costs or scope uncertainties

    A contingency is a percentage or dollar amount added to a construction estimate to account for unforeseen conditions and scope uncertainties.

  3. What is 'quantity takeoff' in the context of Florida construction estimating?

    Answer: The process of measuring and quantifying all materials and labor from construction documents

    Quantity takeoff is the process of measuring all materials, labor, and equipment quantities directly from drawings and specifications.

  4. Which of the following is typically included in a contractor's 'general conditions' costs in a Florida project estimate?

    Answer: Job-site superintendent salary, temporary facilities, and site safety equipment

    General conditions costs include project-specific overhead like superintendent salary, temporary offices, portable toilets, safety equipment, and site fencing.

  5. In Florida public bidding, what is a 'unit price' contract most suitable for?

    Answer: Projects where quantities are uncertain but the type of work is well-defined

    Unit price contracts are ideal when the scope type is known but quantities are uncertain, allowing payment adjustments based on actual quantities installed.

  6. When preparing a Florida construction estimate, what is the typical range for a general contractor's overhead and profit (O&P) markup on subcontractor work?

    Answer: 5–15%

    General contractors in Florida typically apply an overhead and profit markup of 5–15% on subcontractor costs, though this varies by project type and market.