  1. Under Florida's Construction Lien Law, how many days does a lienor typically have to record a claim of lien after the last furnishing of labor or materials?

    Answer: 90 days

    A claim of lien must be recorded within 90 days after the final furnishing of labor, services, or materials to the project.

  2. A subcontractor not in direct contract with the owner must serve what document to preserve lien rights?

    Answer: Notice to Owner

    The Notice to Owner alerts the property owner that a subcontractor or supplier may claim a lien, and must generally be served within 45 days of first furnishing.

  3. What is the purpose of the Contractor's Final Payment Affidavit in Florida?

    Answer: To state that all lienors have been paid or list those still owed before final payment

    A contractor in direct contract with the owner must furnish the Final Payment Affidavit at least 5 days before filing a lien suit, listing unpaid lienors.

  4. How long is a recorded claim of lien valid in Florida before it must be enforced by lawsuit?

    Answer: 1 year

    A claim of lien remains valid for one year from recording, after which it must be enforced through a foreclosure action or it expires.

  5. Which Florida statute chapter governs the Construction Lien Law?

    Answer: Chapter 713

    Chapter 713 of the Florida Statutes sets out the Construction Lien Law and related lienor rights and procedures.

  6. An owner may shorten a lienor's time to file suit by serving what?

    Answer: A Notice of Contest of Lien

    Serving a Notice of Contest of Lien reduces the lienor's enforcement period to 60 days from service.

  7. A Notice of Commencement generally expires after what period unless a different date is specified?

    Answer: 1 year

    Unless it states a longer or shorter effective date, a Notice of Commencement is effective for one year after recording.