  1. A guaranteed maximum price (GMP) contract protects the owner by:

    Answer: Capping the total cost the owner will pay, with savings often shared

    A GMP sets a ceiling on costs the owner pays, with the contractor absorbing overruns above it.

  2. The most effective time to influence project cost with the least expense is during the:

    Answer: Planning and design phase

    Early planning and design decisions have the greatest impact on cost at the lowest change expense.

  3. A crash schedule technique in project management involves:

    Answer: Adding resources to critical activities to shorten duration, usually at added cost

    Crashing shortens the critical path by adding resources, typically increasing cost.

  4. A request for information (RFI) is typically used by a contractor to:

    Answer: Obtain clarification on drawings or specifications from the design team

    An RFI seeks clarification of ambiguous or conflicting design documents.

  5. Value engineering on a construction project aims to:

    Answer: Achieve required functions at the lowest lifecycle cost without sacrificing quality

    Value engineering optimizes function versus cost to deliver required performance economically.

  6. A Gantt chart is most useful for:

    Answer: Displaying activity durations and their timing along a calendar bar chart

    A Gantt chart shows activities as horizontal bars against a timeline for easy scheduling visualization.

  7. In earned value management, a Schedule Performance Index (SPI) greater than 1.0 means:

    Answer: More work has been completed than planned, indicating ahead of schedule

    An SPI above 1.0 shows earned value exceeds planned value, meaning the project is ahead of schedule.