Financial Management for Project Managers Risk Management 4 — Questions and Answers
Question 1: A project's cost estimate has a P80 value of $2.4M and a P50 value of $2.1M. A risk-averse sponsor prefers to fund the project at which level?
- P50 ($2.1M)
- P80 ($2.4M) (Correct answer)
- The average of P50 and P80
- The mode of the cost distribution
Correct answer: P80 ($2.4M)
Funding at P80 means there is an 80% probability that actual costs will not exceed that amount, providing a larger buffer for a risk-averse sponsor.
Question 2: Which of the following is an example of a 'residual risk'?
- A new risk created by the risk response plan
- The remaining exposure after a risk response has been implemented (Correct answer)
- A risk identified after the project has closed
- An unquantified risk with no owner assigned
Correct answer: The remaining exposure after a risk response has been implemented
Residual risk is the level of exposure that remains after a risk response has been applied.
Question 3: A project manager notices that actual cost variance is consistently negative across multiple reporting periods. From a risk management perspective, this MOST likely indicates:
- An unidentified risk has materialized and is affecting costs (Correct answer)
- The risk register is complete and all risks are under control
- The project is performing better than planned
- Contingency reserves are adequate
Correct answer: An unidentified risk has materialized and is affecting costs
Persistent negative cost variance (spending more than planned) often signals that an unplanned risk event is impacting the project.
Question 4: When using a probability and impact matrix, a risk rated 'High' probability and 'High' impact would typically require which response approach?
- Passive acceptance
- Workaround development
- Aggressive response planning (avoid, transfer, or mitigate) (Correct answer)
- Deferral to a later project phase
Correct answer: Aggressive response planning (avoid, transfer, or mitigate)
High/High risks represent the greatest threat to project objectives and demand proactive, aggressive response strategies.
Question 5: A project manager calculates that fixing a defect after delivery will cost $500,000 but preventing it during development costs $50,000. This analysis is BEST described as:
- Cost-benefit analysis of risk response options (Correct answer)
- Net present value comparison
- Break-even analysis
- Sensitivity analysis
Correct answer: Cost-benefit analysis of risk response options
Comparing the cost of prevention versus the cost of failure is a cost-benefit analysis used to justify proactive risk responses.
Question 6: A risk trigger (also called a 'risk symptom' or 'warning sign') is BEST used to:
- Calculate the EMV of a risk event
- Signal that a risk is about to occur, prompting execution of the response plan (Correct answer)
- Determine the probability of a risk materializing
- Identify which project phase a risk belongs to
Correct answer: Signal that a risk is about to occur, prompting execution of the response plan
Risk triggers are indicators that warn the team a risk event is imminent, enabling timely activation of the pre-planned response.
Question 7: Under PMBOK guidance, contingency reserves are BEST described as budget set aside to address:
- Unknown-unknown risks not yet identified
- Known risks that have been identified and analyzed (Correct answer)
- Cost overruns caused by poor scope management
- Vendor price increases on fixed-price contracts
Correct answer: Known risks that have been identified and analyzed
Contingency reserves are specifically allocated for known risks identified in the risk register, while management reserves cover unknown risks.
A project's cost estimate has a P80 value of $2.4M and a P50 value of $2.1M.
A risk-averse sponsor prefers to fund the project at which level?