A project manager calculates a Variance at Completion (VAC) of -$30,000. What is the correct interpretation?
-
A
The project is forecast to finish $30,000 over budget
-
B
The project is forecast to finish $30,000 under budget
-
C
The project is currently $30,000 behind schedule
-
D
The project needs $30,000 more in management reserve