A project manager discovers that a key subcontractor is experiencing cash flow difficulties and may default. Which proactive mitigation is most appropriate?
-
A
Immediately terminate the subcontract and rebid the work
-
B
Negotiate accelerated progress payments in exchange for a price concession or performance bond
-
C
Ignore the issue unless a formal default notice is issued
-
D
Transfer the subcontractor's scope to the client