A project is 60% complete but has only received 40% of its contracted billing value. Which metric directly quantifies this cash flow shortfall?
-
A
Cost Performance Index (CPI)
-
B
Schedule Performance Index (SPI)
-
C
Billing efficiency ratio
-
D
Funding gap variance