A project manager notices that cash outflows are consistently occurring two weeks before the corresponding cash inflows. Which technique best addresses this timing gap?
-
A
Accelerating accounts receivable collection
-
B
Increasing the project contingency reserve
-
C
Delaying vendor contract execution
-
D
Reducing the project scope