A vendor invoice arrives with a 2/10 net 30 payment term. What does this mean for the project manager?
-
A
Pay within 30 days to get a 2% discount
-
B
Get a 2% discount if paid within 10 days, otherwise full amount due in 30 days
-
C
Pay 2% interest if not paid within 10 days
-
D
Pay within 2 days or face a 10% penalty