← All Financial Management for Project Managers Flashcard Decks

Earned Value Management Flashcards

6 cards from real Financial Management for Project Managers practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 Earned Value Management flashcards as text
  1. The Estimate at Completion (EAC) using the most common EVM formula (assuming past CPI continues) is:

    Answer: BAC / CPI

    EAC = BAC / CPI assumes the cost efficiency experienced so far will continue for the remaining work, projecting the final total cost of the project.

  2. Estimate to Complete (ETC) represents:

    Answer: The expected cost to finish the remaining project work

    ETC is the projected cost of completing the remaining scope of work, calculated as EAC - AC.

  3. Variance at Completion (VAC) is defined as:

    Answer: BAC - EAC

    VAC = BAC - EAC; a positive VAC indicates the project is expected to finish under budget, while a negative VAC signals an expected overrun.

  4. A project has BAC = $100,000, EV = $40,000, and AC = $50,000. What is the Cost Performance Index (CPI)?

    Answer: 0.80

    CPI = EV / AC = $40,000 / $50,000 = 0.80, meaning the project is getting only $0.80 of value for every dollar spent.

  5. Planned Value (PV) in EVM represents:

    Answer: The budgeted cost of work scheduled to be done by a specific point in time

    PV (also called BCWS — Budgeted Cost of Work Scheduled) is the authorized budget for the work planned to be completed at any given point in the project schedule.

  6. To-Complete Performance Index (TCPI) based on BAC measures:

    Answer: The cost efficiency required on all remaining work to meet the original budget

    TCPI = (BAC - EV) / (BAC - AC); it tells managers what CPI must be achieved on remaining work to hit the original BAC.