Financial Management for Project Managers Earned Value Management 2 — Questions and Answers
Question 1: The Estimate at Completion (EAC) using the most common EVM formula (assuming past CPI continues) is:
- BAC + AC
- BAC / CPI (Correct answer)
- AC + ETC
- BAC - CV
Correct answer: BAC / CPI
EAC = BAC / CPI assumes the cost efficiency experienced so far will continue for the remaining work, projecting the final total cost of the project.
Question 2: Estimate to Complete (ETC) represents:
- The total cost incurred on the project so far
- The expected cost to finish the remaining project work (Correct answer)
- The total authorized budget for the project
- The variance between earned and planned value
Correct answer: The expected cost to finish the remaining project work
ETC is the projected cost of completing the remaining scope of work, calculated as EAC - AC.
Question 3: Variance at Completion (VAC) is defined as:
- EAC - BAC
- BAC - EAC (Correct answer)
- EV - AC
- PV - EV
Correct answer: BAC - EAC
VAC = BAC - EAC; a positive VAC indicates the project is expected to finish under budget, while a negative VAC signals an expected overrun.
Question 4: A project has BAC = $100,000, EV = $40,000, and AC = $50,000. What is the Cost Performance Index (CPI)?
- 0.80 (Correct answer)
- 0.85
- 0.90
- 1.25
Correct answer: 0.80
CPI = EV / AC = $40,000 / $50,000 = 0.80, meaning the project is getting only $0.80 of value for every dollar spent.
Question 5: Planned Value (PV) in EVM represents:
- The actual cost of work completed
- The budgeted cost of work scheduled to be done by a specific point in time (Correct answer)
- The total budget approved for the project
- The forecasted final cost of the project
Correct answer: The budgeted cost of work scheduled to be done by a specific point in time
PV (also called BCWS — Budgeted Cost of Work Scheduled) is the authorized budget for the work planned to be completed at any given point in the project schedule.
Question 6: To-Complete Performance Index (TCPI) based on BAC measures:
- The cost efficiency required on all remaining work to meet the original budget (Correct answer)
- The schedule efficiency needed to finish on time
- The actual cost efficiency achieved to date
- The variance expected at project completion
Correct answer: The cost efficiency required on all remaining work to meet the original budget
TCPI = (BAC - EV) / (BAC - AC); it tells managers what CPI must be achieved on remaining work to hit the original BAC.
The Estimate at Completion (EAC) using the most common EVM formula (assuming past CPI continues) is: