Which type of cost estimate is typically prepared during the project initiation phase using analogous techniques and carries an accuracy range of -25% to +75%?
-
A
Definitive estimate
-
B
Parametric estimate
-
C
Rough Order of Magnitude (ROM) estimate
-
D
Bottom-up estimate