Which of the following is a valid 'excusable delay' under FAR 49.401 that can prevent a termination for default?
-
A
Contractor's failure to properly manage project cash flow
-
B
Acts of God such as floods or natural disasters
-
C
Subcontractor insolvency caused by poor business practices
-
D
Late delivery of materials ordered after contract award