Under a termination for convenience, what document does the contractor typically submit to the Contracting Officer to resolve incurred costs and fees?
-
A
Request for Equitable Adjustment (REA)
-
B
Termination Settlement Proposal
-
C
Claim under the Contract Disputes Act
-
D
Incurred Cost Submission (ICS)