A contracting officer receives a contractor's request for equitable adjustment (REA) following a government-directed change. What is the primary basis for evaluating the REA?
-
A
The contractor's overall profit margin on the contract
-
B
The actual cost impact causally linked to the government change
-
C
The contractor's historical performance ratings
-
D
The total remaining contract value