Under the FAR, what is the difference between a 'Termination for Convenience' (T4C) and a 'Termination for Default' (T4D)?
-
A
T4C compensates the contractor for work performed; T4D may hold the contractor liable for reprocurement costs
-
B
T4C is initiated by the contractor; T4D is initiated by the Government
-
C
T4D always results in debarment; T4C does not
-
D
T4C applies only to fixed-price contracts; T4D applies only to cost-reimbursement contracts