A contractor submits a bid and later discovers a material error in the estimate. Under Florida law, what is the contractor's BEST course of action?
-
A
Proceed with the contract and absorb the loss
-
B
Notify the owner immediately and request bid withdrawal before award
-
C
Wait until after award to renegotiate the price
-
D
Subcontract all work to limit exposure