A proposal for a cost-plus-fixed-fee contract includes labor rates significantly below industry standards. What is the MOST appropriate government response?
-
A
Accept the rates as proposed since the contractor bears no cost risk
-
B
Perform a cost realism analysis and adjust rates to realistic levels for evaluation purposes
-
C
Reject the proposal as non-responsive
-
D
Accept the rates and reduce the fixed fee to compensate