A force majeure clause in a Florida construction contract typically excuses a party from performance when delays are caused by:
-
A
Labor cost increases
-
B
Material shortages caused by poor planning
-
C
Hurricanes, floods, or other unforeseeable natural disasters
-
D
Subcontractor insolvency