Under the SBA All Small Mentor-Protégé Program, a protégé firm may have joint ventures with its mentor counted as:
Answer: Small business for any federal prime contract or subcontract
Under the All Small Mentor-Protégé Program, a mentor-protégé joint venture is treated as a small business for any federal procurement.
A contractor's subcontracting plan is incorporated into the contract as a material representation, meaning:
Answer: Failure to comply with the plan constitutes a breach of contract subject to liquidated damages
Because the plan is a material contract representation, non-compliance is a breach that can trigger liquidated damages under FAR 52.219-9.
The Summary Subcontract Report (SSR) is submitted:
Answer: Annually by prime contractors with approved subcontracting plans for all contracts with the same agency
The SSR is an annual report rolled up across all contracts with a single agency, providing a cumulative small business subcontracting picture.
Which clause requires contractors to notify the contracting officer before subcontracting more than a specified percentage of work under a small business set-aside?
Answer: FAR 52.219-14, Limitations on Subcontracting
FAR 52.219-14 limits how much of the contract work a small business prime may subcontract to non-small businesses to maintain set-aside integrity.
In a contractor teaming arrangement (CTA), which party bears primary contractual responsibility to the government for contract performance?
Answer: The prime contractor
The prime contractor bears full contractual responsibility to the government; subcontractors are only in privity with the prime.
A small business that is a first-tier subcontractor must be paid within how many days after the prime receives payment from the government, per prompt payment rules?
Answer: 30 days