Under FAR 15.403-4, what is the current threshold requiring certified cost or pricing data for non-commercial items?
Answer: $750,000
FAR 15.403-4(a)(1) requires certified cost or pricing data when the price exceeds $750,000, absent an exception.
Which of the following BEST describes 'adequate price competition' as an exception to certified cost or pricing data?
Answer: Two or more responsible offerors compete independently and the award will be made to the lowest price
FAR 15.403-1(b)(1) defines adequate price competition as existing when two or more responsible offerors compete independently and the award will be made at the lowest price.
A contracting officer is conducting discussions with offerors in the competitive range. Which action is PROHIBITED during discussions?
Answer: Revealing one offeror's technical solution to another offeror
FAR 15.306(e)(1) prohibits the contracting officer from disclosing one offeror's technical solution or any information that would compromise integrity.
Under FAR 15.404-1, price analysis techniques include all of the following EXCEPT:
Answer: Review of certified cost or pricing data
Reviewing certified cost or pricing data is a cost analysis technique under FAR 15.404-1(c), not a price analysis technique.
When an offeror requests a post-award debriefing, how long does the government have to provide it under FAR 15.506?
Answer: 5 business days from request
FAR 15.506(a)(1) requires the debriefing to occur within 5 business days after receipt of a written request.
Under FAR 15.209, what clause must be included in a solicitation when the government intends to award without discussions?
Answer: FAR 52.215-1 with the appropriate alternate
FAR 15.209(a) requires inclusion of FAR 52.215-1 (or its alternate) which informs offerors the government may award without discussions.
What is the purpose of a 'final proposal revision' (FPR) in negotiated acquisitions?
Answer: To allow offerors one opportunity to improve proposals after discussions
FAR 15.307(b) requires the contracting officer to request final proposal revisions after discussions to allow offerors to revise their proposals.