FAC Risk Assessment & Underwriting 2 — Questions and Answers
Question 1: Under FAR Part 16, which contract type places the MOST financial risk on the government when cost is uncertain?
- Firm-Fixed-Price (FFP)
- Cost-Plus-Fixed-Fee (CPFF) (Correct answer)
- Fixed-Price-Incentive (FPI)
- Indefinite-Delivery Indefinite-Quantity (IDIQ)
Correct answer: Cost-Plus-Fixed-Fee (CPFF)
CPFF contracts reimburse all allowable costs plus a fixed fee, so the government bears essentially all cost risk if expenditures exceed estimates.
Question 2: A contracting officer is assessing risk for a sole-source award. Which factor MOST increases the risk that the award price will be unreasonable?
- The contractor has extensive past performance data
- There is no competitive market to benchmark pricing (Correct answer)
- The requirement is for commercial items
- The period of performance is less than one year
Correct answer: There is no competitive market to benchmark pricing
Without competition, there is no market pricing signal, making it difficult to establish that the negotiated price is fair and reasonable.
Question 3: Which risk mitigation tool allows the government to reduce schedule risk by requiring a contractor to identify critical path milestones in advance?
- Integrated Baseline Review (IBR) (Correct answer)
- Quality Assurance Surveillance Plan (QASP)
- Independent Government Cost Estimate (IGCE)
- Past Performance Questionnaire (PPQ)
Correct answer: Integrated Baseline Review (IBR)
An IBR assesses whether the contractor's performance measurement baseline is realistic and whether critical path milestones are achievable.
Question 4: When performing price analysis on a proposed contract action, which technique compares the offered price to prices found in catalog or market data?
- Comparison with competitive offers
- Comparison with prior prices paid
- Comparison with commercial catalog prices (Correct answer)
- Visual price analysis
Correct answer: Comparison with commercial catalog prices
Comparing proposed prices to established catalog or market prices is a standard price analysis technique under FAR 15.404-1(b).
Question 5: A performance bond in federal contracting primarily protects the government against which risk?
- Contractor fraud during proposal submission
- Contractor failure to complete the work as specified (Correct answer)
- Subcontractor payment disputes
- Defective pricing at contract close-out
Correct answer: Contractor failure to complete the work as specified
A performance bond guarantees that the surety will complete the project or pay damages if the contractor fails to fulfill contract requirements.
Question 6: Under the FAC-C program, risk identification during source selection BEST aligns with which phase of the acquisition process?
- Contract administration
- Pre-award planning (Correct answer)
- Contract close-out
- Debriefing
Correct answer: Pre-award planning
Risk identification and mitigation strategies should be developed during pre-award planning so they can be incorporated into contract terms and evaluation criteria.
Question 7: Which document formally records identified risks, their likelihood, potential impact, and planned responses for a federal acquisition?
- Independent Government Cost Estimate (IGCE)
- Acquisition Plan (AP)
- Risk Register (Correct answer)
- Market Research Report
Correct answer: Risk Register
A Risk Register is the standard tool for capturing, tracking, and managing identified risks throughout an acquisition lifecycle.
Under FAR Part 16, which contract type places the MOST financial risk on the government when cost is uncertain?