  1. Under the Contract Disputes Act (CDA), what is the statute of limitations for submitting a contractor claim?

    Answer: 6 years from accrual

    The CDA requires that contractor claims be submitted within 6 years after the claim accrues.

  2. A contracting officer issues a final decision on a claim. Within how many days must a contractor appeal to the Armed Services Board of Contract Appeals (ASBCA)?

    Answer: 90 days

    A contractor must appeal a contracting officer's final decision to a Board of Contract Appeals within 90 days of receipt.

  3. Which FAR clause is mandatory in all contracts subject to the Contract Disputes Act and governs the disputes process?

    Answer: FAR 52.233-1, Disputes

    FAR 52.233-1, Disputes, is the mandatory clause that establishes the disputes process under the CDA.

  4. A contractor submits a claim for $175,000. The contracting officer believes the amount is inflated. What must the CO do before issuing a final decision?

    Answer: Investigate and issue a final decision within 60 days

    For claims over $100,000, the CO must issue a final decision within 60 days or notify the contractor of a new decision date.

  5. What distinguishes a 'claim' from a 'request for equitable adjustment' (REA) under the CDA?

    Answer: A claim is a written demand seeking a CO final decision as a matter of right

    A claim is a written demand seeking a contracting officer's final decision as a matter of right, while an REA is a request for voluntary adjustment before a claim is filed.

  6. Interest on contractor claims under the CDA begins accruing on which date?

    Answer: Date the claim is submitted to the CO

    Under the CDA, interest on contractor claims accrues from the date the claim is submitted to the contracting officer.

  7. A contractor submits a claim exceeding $100,000 without a certification. What is the legal effect?

    Answer: The claim is defective but can be corrected without losing the original submission date

    A defective certification does not deprive a Board or Court of jurisdiction; the contractor may correct it and the original submission date is preserved.