EVM Certification Practice Test
EVM Certification Forecasting & Estimates at Completion 3
A project has CPI = 0.75 and BAC = $400,000.
Using EAC = BAC / CPI, what is the EAC?
Select your answer
A
$480,000
B
$510,000
C
$533,333
D
$400,000