ETC Project Management & Documentation 3 — Questions and Answers
Question 1: In Earned Value Management (EVM), what does SPI stand for?
- Schedule Performance Index (Correct answer)
- Scope Planning Index
- Status Progress Indicator
- Standard Project Integration
Correct answer: Schedule Performance Index
SPI (Schedule Performance Index) equals Earned Value divided by Planned Value and indicates schedule efficiency.
Question 2: A project has a CPI of 0.85. What does this indicate?
- The project is 15% ahead of schedule
- The project is spending 15% more than planned per unit of work (Correct answer)
- The project will finish 15% early
- The project has 15% more scope than originally planned
Correct answer: The project is spending 15% more than planned per unit of work
A CPI less than 1.0 means the project is over budget — spending more than planned for the work accomplished.
Question 3: Which scheduling technique calculates the longest path through a project network to determine the minimum project duration?
- PERT analysis
- Critical Path Method (CPM) (Correct answer)
- Resource leveling
- Monte Carlo simulation
Correct answer: Critical Path Method (CPM)
The Critical Path Method identifies the longest sequence of dependent tasks, determining the shortest possible project duration.
Question 4: What is the purpose of a change control board (CCB) in project management?
- To assign team members to tasks
- To review and approve or reject proposed changes (Correct answer)
- To document project risks
- To conduct performance reviews
Correct answer: To review and approve or reject proposed changes
A CCB is a formally constituted group responsible for evaluating, approving, deferring, or rejecting changes to the project.
Question 5: Which document type provides a detailed written description of work to be performed by a contractor or vendor?
- Project Charter
- Statement of Work (SOW) (Correct answer)
- Risk Register
- Procurement Plan
Correct answer: Statement of Work (SOW)
A Statement of Work (SOW) describes in detail the work to be delivered by a vendor or contractor under a contract.
Question 6: In project documentation, what is the primary purpose of a lessons learned register?
- To track pending action items
- To capture knowledge for improving future projects (Correct answer)
- To list approved vendors
- To record daily timesheets
Correct answer: To capture knowledge for improving future projects
A lessons learned register captures knowledge gained during the project so future projects can benefit from past experiences.
Question 7: When a project manager compresses the schedule by overlapping activities that were originally planned in sequence, this technique is called:
- Crashing
- Resource smoothing
- Fast tracking (Correct answer)
- Schedule baselining
Correct answer: Fast tracking
Fast tracking overlaps or parallels tasks that were originally planned in sequence, which can shorten the schedule but increases risk.
In Earned Value Management (EVM), what does SPI stand for?