ETC Construction Methods & Field Operations Flashcards
6 cards from real ETC practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 6 ETC Construction Methods & Field Operations flashcards as text
What does a construction daily report document?
Answer: Weather, personnel, equipment, work performed, and any issues encountered each day
A daily field report documents weather conditions, workers on site, equipment used, work completed, and any problems or observations for that day.
What is the purpose of a geotextile fabric in construction?
Answer: To separate, filter, reinforce, or drain in soil and aggregate applications
Geotextiles are permeable fabrics used in civil engineering for separation of soil layers, filtration, reinforcement, drainage, and erosion protection.
What does 'punch list' mean at project completion?
Answer: A final list of incomplete or deficient items the contractor must correct before final acceptance
A punch list is a document prepared near project completion listing items that do not meet contract requirements and must be corrected before final payment.
What is the function of a construction testing laboratory during a project?
Answer: To perform independent material testing to verify compliance with specifications
A testing laboratory performs independent tests on materials such as soils, concrete, and asphalt to verify they meet project specification requirements.
What is the purpose of formwork in concrete construction?
Answer: To provide the mold that holds fresh concrete in shape until it hardens
Formwork is temporary structure that molds and supports fresh concrete in the desired shape until it gains sufficient strength to be self-supporting.
What does a Request for Information (RFI) accomplish on a construction project?
Answer: It asks the engineer or owner to clarify or provide missing information from the contract documents
An RFI is a formal written request from the contractor to the designer or owner asking for clarification of contract documents to resolve ambiguities or conflicts.