According to NFPA 70E, what is required before an electrician opens an energized electrical panel cover for inspection?
-
A
A verbal authorization from a supervisor
-
B
An energized electrical work permit and appropriate PPE based on the arc flash hazard analysis
-
C
A standard work order and safety glasses
-
D
Written approval from the facility manager only