ERP ERP Project Management & Implementation Lifecycle 2 — Questions and Answers
Question 1: Which document formally authorizes the start of an ERP project and names the project sponsor?
- Statement of Work
- Project Charter (Correct answer)
- Request for Proposal
- Change Control Form
Correct answer: Project Charter
The Project Charter is the formal document that authorizes the project, defines high-level scope, and identifies the project sponsor.
Question 2: In ERP project management, what is a RAID log used to track?
- Risks, Assumptions, Issues, and Dependencies (Correct answer)
- Reports, Approvals, Installations, and Deliverables
- Resources, Activities, Integrations, and Data
- Requirements, Architecture, Implementation, and Deployment
Correct answer: Risks, Assumptions, Issues, and Dependencies
A RAID log is a project management tool that tracks Risks, Assumptions, Issues, and Dependencies throughout the implementation.
Question 3: What is the purpose of a cutover plan in an ERP implementation?
- Define the project budget
- Detail the step-by-step activities required to transition from the old system to the new ERP (Correct answer)
- Document system architecture
- Outline vendor payment schedules
Correct answer: Detail the step-by-step activities required to transition from the old system to the new ERP
A cutover plan documents every task, owner, and timing needed to safely switch operations from the legacy system to the new ERP.
Question 4: Which milestone marks the formal end of the ERP implementation project and transition to support operations?
- System Integration Testing completion
- Go-Live
- Hypercare period end / Project Closure (Correct answer)
- UAT sign-off
Correct answer: Hypercare period end / Project Closure
Project Closure occurs after the hypercare stabilization period ends, with lessons learned documented and the system handed to support teams.
Question 5: What is the primary goal of the hypercare phase immediately following ERP go-live?
- Begin planning the next ERP upgrade
- Provide intensive support to stabilize operations and resolve critical issues quickly (Correct answer)
- Complete final data migration loads
- Train the project team on methodology
Correct answer: Provide intensive support to stabilize operations and resolve critical issues quickly
Hypercare is a dedicated post-go-live support period with heightened resources available to rapidly resolve issues and stabilize the system.
Question 6: In ERP projects, what does a RACI matrix define?
- System security roles and permissions
- Roles: Responsible, Accountable, Consulted, and Informed for each task (Correct answer)
- Resource allocation and cost tracking
- Risk assessment and compliance indicators
Correct answer: Roles: Responsible, Accountable, Consulted, and Informed for each task
A RACI matrix clarifies team roles by identifying who is Responsible, Accountable, Consulted, and Informed for every project task.
Which document formally authorizes the start of an ERP project and names the project sponsor?