Under FERC Order 1000, which of the following is a key requirement for regional transmission planning?
-
A
Elimination of federal cost allocation for all projects
-
B
Removal of federal rights of first refusal for incumbent utilities in competitive transmission
-
C
Mandatory rate base treatment for all merchant transmission lines
-
D
Prohibition of interregional transmission coordination