  1. Under the RRP Rule, how long must renovation firms retain records documenting pre-renovation disclosure to owners and occupants?

    Answer: 3 years following the renovation

    The EPA RRP Rule requires renovation firms to retain all pre-renovation disclosure records, including signed acknowledgments or certificates of mailing, for 3 years following the renovation.

  2. If the 'Renovate Right' pamphlet is sent by mail rather than delivered in person, how many days before the renovation must it be mailed?

    Answer: 7 days

    If the pamphlet is mailed rather than hand-delivered, it must be mailed at least 7 days before the renovation begins to account for standard mail delivery time.

  3. What must a renovator do if an adult occupant of target housing refuses to sign the acknowledgment of pamphlet receipt?

    Answer: The renovator must note the refusal and have at least one witness sign the documentation

    When an occupant refuses to sign an acknowledgment, the renovator or a firm representative must note the refusal on the acknowledgment form and have at least one witness sign and date the form.

  4. What information must a renovation notice posted in a common area of a multi-unit building include?

    Answer: A description of the nature and location of the renovation and the planned start date

    Common area renovation notices must describe the nature and location of the renovation and state the planned start date so that residents can take appropriate precautions.

  5. For an emergency renovation that cannot be postponed, when must the 'Renovate Right' pamphlet be provided to occupants?

    Answer: Before work begins if possible, and in all cases within 30 days after completion

    For emergency renovations, the RRP Rule allows the pamphlet to be provided as soon as possible before or during the renovation, and in all cases within 30 days after the renovation is completed.

  6. Under what regulation is the EPA's pre-renovation education and disclosure requirement for lead-based paint codified?

    Answer: 40 CFR Part 745

    The EPA's RRP Rule, including all pre-renovation education requirements, is codified at 40 CFR Part 745, which covers lead-based paint poisoning prevention in certain residential structures.

  7. When common areas of a multi-unit building are being renovated, which tenants must receive pre-renovation notification?

    Answer: All tenants in the building, regardless of proximity to the work

    When common areas are renovated, the pre-renovation notice must be provided to all tenants of the affected housing, since lead dust can travel throughout a building and affect all occupants.