Enforcement and Reporting Flashcards
7 cards from real Environmental Compliance Inspector practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Enforcement and Reporting flashcards as text
A Discharge Monitoring Report (DMR) submitted 45 days after the deadline is considered what type of violation?
Answer: Reporting violation
Late submission of a DMR constitutes a reporting violation, which is separately enforceable from effluent limit exceedances.
Under the Clean Air Act, which enforcement tool allows EPA to recover the economic benefit a violator gained by not complying?
Answer: Penalty calculation using BEN model
EPA's BEN (Benefit of Noncompliance) model calculates the economic savings a violator realized, which forms the baseline for penalty assessment.
What is a Supplemental Environmental Project (SEP) in the context of enforcement settlements?
Answer: An environmentally beneficial project a violator agrees to perform in exchange for penalty mitigation
SEPs are projects that provide environmental or public health benefits beyond compliance, accepted in settlement to partially offset monetary penalties.
Which agency division is typically responsible for referring criminal environmental cases to the Department of Justice?
Answer: EPA Criminal Investigation Division (CID)
EPA's Criminal Investigation Division (CID) investigates criminal environmental violations and coordinates referrals to the DOJ for prosecution.
A facility challenges an EPA administrative compliance order in court. What standard of judicial review generally applies?
Answer: Arbitrary and capricious standard under the APA
Courts review EPA administrative orders under the arbitrary and capricious standard of the Administrative Procedure Act, deferring to agency expertise.
Under TSCA, what must an inspector verify when reviewing a company's PCB disposal records?
Answer: Proper manifesting, storage time limits, and use of approved disposal facilities
PCB disposal compliance under TSCA requires verifying manifests, storage duration compliance, and confirmation that approved incinerators or landfills were used.
When an enforcement case results in a consent decree, which court action is required to make it binding?
Answer: Entry by a federal district court judge
A consent decree must be entered (signed and accepted) by a federal district court judge to become a legally enforceable court order.