A project team is selecting between two stormwater management approaches. Approach A has lower upfront cost but higher long-term maintenance. Under Envision's lifecycle thinking, which factor should PRIMARILY drive the decision?
-
A
The approach with the lowest first cost to stay within budget
-
B
Total cost of ownership over the infrastructure's design life
-
C
The preference of the construction contractor
-
D
The approach most commonly used in the region