← All EMP Flashcard Decks

Compliance Reporting & Documentation Flashcards

7 cards from real EMP practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Compliance Reporting & Documentation flashcards as text
  1. A hospital energy manager discovers that sub-meter data used in a Joint Commission sustainability report was recorded with a ±15% error. What M&V best practice should have prevented this?

    Answer: Establishing meter calibration and uncertainty documentation per IPMVP guidelines

    IPMVP requires documenting meter accuracy, calibration schedules, and acceptable uncertainty thresholds to ensure data quality in M&V reports.

  2. Which statement correctly describes the documentation requirement for a Demand Response (DR) event under a utility interruptible tariff?

    Answer: The facility must log actual load reduction, duration, and any non-performance with supporting meter data

    Interruptible tariff programs require customers to document their actual load curtailment, event timestamps, and any non-compliance events to reconcile with utility payment calculations.

  3. A company pursuing LEED O+M: Existing Buildings certification needs to document energy use. What minimum period of continuous energy data must be collected before submitting for certification?

    Answer: 12 months

    LEED O+M requires a minimum of 12 consecutive months of energy performance data to establish a valid basis for certification under the Energy and Atmosphere credits.

  4. Under the Clean Air Act Title V operating permit program, what must an energy manager document if a facility switches from natural gas to fuel oil for emergency generation affecting reported NOx emissions?

    Answer: A Significant Permit Modification or deviation report filed with the state agency

    Title V permits require facilities to notify the permitting authority of deviations or changes that may affect regulated air emissions, which can trigger a permit modification requirement.

  5. In a retro-commissioning (RCx) project, what document serves as the authoritative record of identified deficiencies, implemented measures, and verified savings?

    Answer: Final RCx Report including the Master List of Findings (MLF)

    The Final Retro-Commissioning Report, anchored by the Master List of Findings, documents all measures investigated, implemented, and verified with associated energy and cost savings.

  6. Which federal regulation requires large federal agencies to report annual energy and water intensity data to the Department of Energy via the Federal Energy Management Program (FEMP)?

    Answer: Executive Order 13693 / EO 14057 and the Energy Policy Act of 2005 Section 543

    EO 14057 (and its predecessor EO 13693) along with EPACT 2005 Section 543 require federal agencies to track and report energy and water intensity reduction progress annually to DOE/FEMP.

  7. A corporate sustainability report claims a 30% reduction in Scope 1 emissions. Under the GHG Protocol, what documentation is required to support this claim's accuracy?

    Answer: Activity data sources, emission factors applied, calculation methodology, and data quality assessment

    The GHG Protocol requires organizations to document the activity data used, emission factors, calculation methodology, and a data quality assessment to support any emission inventory claim.