For a separately derived system such as a step-down transformer, where must the system bonding jumper be installed per NEC 250.30(A)(1)?
-
A
At the first overcurrent device downstream of the transformer
-
B
At the transformer primary terminals
-
C
At the source of the separately derived system
-
D
At the remote panelboard served by the transformer