EGSA System Troubleshooting and Maintenance 4 — Questions and Answers
Question 1: A three-phase generator produces balanced voltage at no load, but voltage becomes severely unbalanced under load. What is the most probable cause?
- Incorrect fuel injection timing
- Single-phasing due to an open stator winding or blown phase fuse (Correct answer)
- Incorrect oil viscosity
- Faulty air filter restriction indicator
Correct answer: Single-phasing due to an open stator winding or blown phase fuse
An open stator winding or blown phase fuse causes one phase to lose voltage under load, creating severe three-phase imbalance.
Question 2: What does the acronym MTBF represent, and why is it significant in generator maintenance planning?
- Maximum Time Between Faults — limits warranty claims
- Mean Time Between Failures — used to predict maintenance intervals and reliability (Correct answer)
- Minimum Transfer Bus Frequency — sets paralleling thresholds
- Master Terminal Block Function — defines wiring hierarchy
Correct answer: Mean Time Between Failures — used to predict maintenance intervals and reliability
MTBF (Mean Time Between Failures) is a reliability metric used to schedule preventive maintenance and predict when components are likely to fail.
Question 3: Which procedure should be performed before removing a high-voltage generator set from service for internal inspection?
- Run the engine at full load for 30 minutes
- Perform a LOTO (Lockout/Tagout) procedure on all energy sources (Correct answer)
- Increase coolant temperature to purge system
- Verify oil pressure is above minimum
Correct answer: Perform a LOTO (Lockout/Tagout) procedure on all energy sources
Lockout/Tagout (LOTO) must be applied to all energy sources before internal inspection to prevent accidental energization.
Question 4: A generator's starting battery consistently shows low voltage after a week of standby. The battery charger output is verified correct. What is the most likely cause?
- Low engine oil level draining the battery
- A parasitic load or leakage current discharging the battery between tests (Correct answer)
- Incorrect coolant mixture
- Worn fan belt causing charging failure
Correct answer: A parasitic load or leakage current discharging the battery between tests
A parasitic drain or leakage current not related to the charger circuit will slowly discharge the battery between charge events.
Question 5: What is the function of a diesel engine's prelube system in a generator application?
- Filters fuel before injection
- Supplies oil pressure to engine bearings before cranking to reduce startup wear (Correct answer)
- Regulates coolant flow during warmup
- Controls exhaust backpressure
Correct answer: Supplies oil pressure to engine bearings before cranking to reduce startup wear
A prelube system circulates oil through bearings before engine cranking, preventing the dry-start wear that accounts for most mechanical failures.
Question 6: When testing a generator's voltage regulator response to a sudden load application, the acceptable transient voltage dip and recovery time are typically specified in which document?
- The transfer switch installation manual
- The generator manufacturer's technical specification or NEMA MG-1 standards (Correct answer)
- The building electrical permit
- The engine coolant specification sheet
Correct answer: The generator manufacturer's technical specification or NEMA MG-1 standards
Generator transient response limits for voltage dip and recovery are defined in the manufacturer's technical specification and NEMA MG-1 standards.
Question 7: A diesel generator experiences a sudden loss of load due to a breaker trip. The resulting overspeed causes a high-RPM shutdown. What component is primarily responsible for preventing overspeed?
- The automatic voltage regulator
- The engine governor and overspeed protection relay (Correct answer)
- The coolant thermostat
- The oil pressure switch
Correct answer: The engine governor and overspeed protection relay
The engine governor controls fuel to limit speed, and an overspeed relay provides backup shutdown protection if governor response is insufficient.
A three-phase generator produces balanced voltage at no load, but voltage becomes severely unbalanced under load.
What is the most probable cause?