Recovery Strategy & Planning Flashcards

7 cards from real DRI practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Recovery Strategy & Planning flashcards as text
  1. Which metric defines the maximum tolerable length of time that a business process can be offline before the impact becomes unacceptable?

    Answer: Maximum Tolerable Downtime (MTD)

    MTD (also called MTPD) is the absolute upper limit of downtime an organization can survive, and it drives the RTO and other recovery targets.

  2. A company replicates data to an offsite facility every four hours. What does this replication interval represent?

    Answer: Recovery Point Objective

    The RPO defines how much data loss is acceptable, and a four-hour replication cycle means up to four hours of data could be lost in a disaster.

  3. When selecting a recovery strategy, which factor most directly constrains the range of feasible options?

    Answer: Cost versus recovery time trade-off

    Cost and recovery time have an inverse relationship — faster recovery requires greater investment — making this trade-off the primary constraint on strategy selection.

  4. What is the primary purpose of a Continuity of Operations Plan (COOP)?

    Answer: To ensure essential government or organizational functions continue during a disruption

    A COOP focuses on maintaining mission-essential functions during and after a disruption, particularly used in government and public-sector contexts.

  5. In a hot site strategy, what is the expected activation time when a disaster is declared?

    Answer: Minutes to hours

    Hot sites are fully equipped and operational, so failover can occur within minutes to hours of a disaster declaration.

  6. Which recovery strategy approach involves two organizations agreeing to host each other's operations in the event of a disaster?

    Answer: Reciprocal agreement

    A reciprocal agreement is a mutual aid arrangement where two organizations commit to providing space and resources to each other during a disaster.

  7. What term describes the documented set of procedures used to move operations from a primary site to an alternate site?

    Answer: Activation and Relocation Plan

    An Activation and Relocation Plan details the specific steps, roles, and procedures required to shift operations to an alternate facility after a disaster declaration.