During a digital imaging lab upgrade, a stakeholder requests adding color calibration hardware after the project scope was finalized. This is best handled through:
-
A
Immediate implementation to satisfy the stakeholder
-
B
A formal change control process
-
C
Ignoring the request until project close
-
D
Verbal approval from the project sponsor