← All DIS Flashcard Decks

Technology Project Management Flashcards

7 cards from real DIS practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Technology Project Management flashcards as text
  1. During a digital imaging system implementation, a project manager holds a lessons-learned session. This activity is most closely associated with which process group?

    Answer: Closing

    Lessons-learned sessions are a key closing process activity to capture knowledge for future projects.

  2. A project sponsor for a radiology imaging upgrade requests a status update. The most effective format to convey schedule and budget performance concisely is:

    Answer: Executive dashboard with key metrics

    Executive dashboards provide high-level KPIs that sponsors need without unnecessary detail.

  3. Which estimating technique uses the actual duration or cost of a similar past digital imaging project as the primary basis for a new estimate?

    Answer: Analogous estimating

    Analogous estimating leverages historical data from comparable projects to produce quick estimates.

  4. A project team implementing a hospital's PACS system discovers an undocumented integration requirement late in execution. The project manager should:

    Answer: Submit a change request and assess schedule impact

    Undocumented requirements that emerge during execution must go through formal change control to manage scope and schedule impact.

  5. Schedule Variance (SV) is calculated as:

    Answer: Earned Value minus Planned Value

    SV = EV − PV; a negative SV indicates the project is behind schedule.

  6. In a digital imaging project, a Work Breakdown Structure (WBS) is primarily used to:

    Answer: Decompose project scope into manageable deliverables

    The WBS hierarchically breaks down all project work into smaller, manageable components.

  7. A project manager notices that recurring vendor delays are impacting the imaging hardware delivery schedule. The most proactive response is to:

    Answer: Update the risk register and implement the contingency plan

    Recurring delays indicate a risk has materialized; implementing the contingency plan is the prescribed proactive response.