During a digital imaging system implementation, a project manager holds a lessons-learned session. This activity is most closely associated with which process group?
Answer: Closing
Lessons-learned sessions are a key closing process activity to capture knowledge for future projects.
A project sponsor for a radiology imaging upgrade requests a status update. The most effective format to convey schedule and budget performance concisely is:
Answer: Executive dashboard with key metrics
Executive dashboards provide high-level KPIs that sponsors need without unnecessary detail.
Which estimating technique uses the actual duration or cost of a similar past digital imaging project as the primary basis for a new estimate?
Answer: Analogous estimating
Analogous estimating leverages historical data from comparable projects to produce quick estimates.
A project team implementing a hospital's PACS system discovers an undocumented integration requirement late in execution. The project manager should:
Answer: Submit a change request and assess schedule impact
Undocumented requirements that emerge during execution must go through formal change control to manage scope and schedule impact.
Schedule Variance (SV) is calculated as:
Answer: Earned Value minus Planned Value
SV = EV − PV; a negative SV indicates the project is behind schedule.
In a digital imaging project, a Work Breakdown Structure (WBS) is primarily used to:
Answer: Decompose project scope into manageable deliverables
The WBS hierarchically breaks down all project work into smaller, manageable components.
A project manager notices that recurring vendor delays are impacting the imaging hardware delivery schedule. The most proactive response is to:
Answer: Update the risk register and implement the contingency plan
Recurring delays indicate a risk has materialized; implementing the contingency plan is the prescribed proactive response.